Week 44

Week 44

This week has been productive. It is sometimes difficult to see the amount of progress when they are working indoors and in the elevator pit!   Elevator Pit Footings Dug for foundation Rebar install prior to concrete pour Concrete base slab poured Concrete tested,...
Week 43

Week 43

Zone D (Chapel to Spitzer Building) Roofing work complete with slate being added. Electrical Rough-In is ongoing. Plumbing has been inspected. Next up: Fur out walls and frame in columns.  Zone C The rebar is onsite and the plan is finalized for the elevator pit....
week 41

week 41

Now that we are back in the Sanctuary work has focused primarily on Zone D (Chapel to Spitzer Building) – Masons have worked on the gable roof for the new, smaller Fellowship Hall – Framing inside of Zone D for various offices/spaces The Schedule shows...
Back in the Sanctuary!

Back in the Sanctuary!

  Enter through the doors to the new vestibule by the porte cochere (see image below). Note: The new restrooms are not yet complete. Restrooms available on all levels of the Spitzer...
Weeks 38 & 39

Weeks 38 & 39

Flooring complete in the Barron Hall Connector! Drywall has been added to the low wall.   The Sanctuary: Vestibule painting and flooring is complete! Temporary power for the lights has been added. Intent for Sanctuary to be available on 11/9.  Staff updated and...
Week 37

Week 37

The admin area is looking good as furniture and artwork are being added to offices and common areas! The Sanctuary is where the most signicant work has been done this week: Organ and piano have been moved onto the chancel. Chancel stairs and risers set to be completed...