Sanctuary Flooring in progress for the new chancel (see picture)! SHEEP parking lot Second pour complete for infiltration pit (expect approximately 1 month before we can drive on it) Zone B (Admin Offices) Fire alarm system is being updated Handrails installed in...
Sanctuary: Framing of Narthex started (see picture) Plywood for the Chancel rail delivered Glass measured for Sanctuary storefront small outdoor area between Sanctuary and ramp prepped for pea gravel and drain Zone B: The carpet tiles and base completed…stairs...
The infiltration pit is prepped for concrete. Zone B: The carpet has arrived and there are tentative plans to install this weekend! Zone D: The steel for foundation support was delivered and installed. Next will be removal of the temporary shoring and move to the...
The picture shows the infiltration pit at the rear parking lot. This is a water mitigation pit that absorbs the water, yet still allows cars to park once complete. We expect the pervious concrete pour to start soon, which takes longer to cure than other concrete, and...
Zone B: Walls ready for final coat of paint, casework/cabinetry installed on upper and lower levels (see picture), as well as mason work on dormers. Hopefully staff will move within a month! Zone D: work on new sewer line from basement to the city system; concrete...
SHEEP Parking Lot: The infiltration pit is now complete and awaiting inspection. The next step is adding rocks and compacting them before pouring the permeable concrete surface, which allows us to keep our parking spaces. This should be ready prior to the start of the...