Work has continued at a reasonable pace during December. Most of the current work is concrete cutters removing the old Sanctuary stairs, prepping the new ramp for concrete pour in Zone D, and prepping elevator area for concrete walls. Bathrooms in the Chapel hallway have been demo’d…design team working on flooring, wall, and countertop options. We expect work to slow during the next 2 weeks with the holidays.