This week has been productive. It is sometimes difficult to see the amount of progress when they are working indoors and in the elevator pit!
 
Elevator Pit
  • Footings Dug for foundation
  • Rebar install prior to concrete pour
  • Concrete base slab poured
  • Concrete tested, rebar verified by ind team
Zone D
  • Rough framing of walls
  • Tie in new water to construction area
  • Exhaust vent installed in roof
  • Finish rough wood frame
  • Demo mens/womens bathrooms
  • Dig out ramp area, prep for concrete

Sanctuary

  • Paint stairwell up to balcony
  • Porte cochere timber replacement