Zone D (Chapel to Spitzer Building)
- Roofing work complete with slate being added.
- Electrical Rough-In is ongoing.
- Plumbing has been inspected.
- Next up: Fur out walls and frame in columns.
Zone C
- The rebar is onsite and the plan is finalized for the elevator pit.
- Crews working to prep the layout for a concrete pour.
The Sanctuary Balcony is OPEN! We are expecting a new paint job, but it is accessible and usable for all services.