The admin area is looking good as furniture and artwork are being added to offices and common areas!

The Sanctuary is where the most signicant work has been done this week:

  • Organ and piano have been moved onto the chancel.
  • Chancel stairs and risers set to be completed next week.
  • Drywall was completed in the Vestibule and it’s ready for paint on Monday.
  • Brick work complete in the enclosed gravel area.

Elevator Pit: Gravel laid and ready for the concrete foundation to be poured.