Sanctuary:

  • Framing of Narthex started (see picture)
  • Plywood for the Chancel rail delivered
  • Glass measured for Sanctuary storefront
  • small outdoor area between Sanctuary and ramp prepped for pea gravel and drain

Zone B: The carpet tiles and base completed…stairs remain!

  • Frames and doors installed in connector between Barron Hall and offices
  • Patch and touch up work on walls
  • Roofers continue work on dormers
  • Plumbers onsite to prep for inspection
  • Clean up starting for inspection

Zone D: The steel for foundation support was delivered and installed. Next will be removal of the temporary shoring and move to the exterior wall before it is demolished and rebuilt.