Sanctuary:
- Framing of Narthex started (see picture)
- Plywood for the Chancel rail delivered
- Glass measured for Sanctuary storefront
- small outdoor area between Sanctuary and ramp prepped for pea gravel and drain
Zone B: The carpet tiles and base completed…stairs remain!
- Frames and doors installed in connector between Barron Hall and offices
- Patch and touch up work on walls
- Roofers continue work on dormers
- Plumbers onsite to prep for inspection
- Clean up starting for inspection
Zone D: The steel for foundation support was delivered and installed. Next will be removal of the temporary shoring and move to the exterior wall before it is demolished and rebuilt.