The picture shows the infiltration pit at the rear parking lot. This is a water mitigation pit that absorbs the water, yet still allows cars to park once complete. We expect the pervious concrete pour to start soon, which takes longer to cure than other concrete, and has to be done in stages. Best guess is 5 weeks before we’ll be able to park on it.
Misc: The sewer line was replaced and tied into the city due to collapsed pipes discovered in the construction. This add-on project was necessary, but not considered part of the REACH campaign.
Zone B: Painting complete! Currently waiting on carpet tiles and baseboards to arrive for installation. Internet lines to be attached next week. Following these updates, the admin office should be ready for occupancy. The dormers were also updated with brick.
Zone D: Concrete poured for the foundation areas in the long hallway. Steel foundations possibly added next week.
Sanctuary: Concrete poured on multiple areas around the Sanctuary and brick infil around the old windows that were removed. The grated area near the ramp room was waterproofed to help with flooding, as well as water rerouted.