Work in Zone B has been delayed a bit while the HVAC was turned on. There are several updates that still need to be completed, but the system is now on and operational. We expect flooring to start on Monday as a result.
Storefront doors being installed in the walkway connector to Barron Hall as well as updates to the HVAC diffusers in that space. The new wall in the columbarium is nearly completed and awaiting new niches!
Finally, infiltration pit work has begun in the SHEEP parking lot. This pit will eventually capture water run off from the building. It will have a permeable surface allowing water flow, but also allowing us to park on top of it when completed. In other words, we won’t lose those parking spots. Eventually another infiltration pit will be placed in the parking lot near Treetop coffee.
Reminder: Both worship services will be in Barron Hall until Sanctuary renovations are complete.