Lots of work this week, particularly in Zone B.  The ceiling grid is complete and most of the new LED lights hve been installed.  The difference is dramatic!  Flooring is planned to begin next Tuesday as well as beginning  the work necessary to turn the HVAC system back on.  Also, storefront windows have been installed in the covered walkway between admin and Barron Hall.  Glass also installed in the dormers on 2nd floor.

The other major project this week was install of 17 micro piles for foundation in the elevator pit.  Excavation begin in this area to dig out for structural stabilization as well.

Reminder: Both worship services will be in Barron Hall until Sanctuary renovations are complete (appx. 6-8 weeks).