This week construction began on the Sanctuary.  On Monday the organ was moved in preparation.  Contractors began work in the Sanctuary and have moved quickly.  The chancel is completely rebuilt, although finishing work remains.  The crew also began to demo the outside of the Sanctuary in preparation for the new Narthex leading into the Ramp room.

Reminder: Both worship services will be in Barron Hall until renovations are complete.

The ceiling grid is being installed this week in Zone B with HVAC work to begin in appx 2 weeks.  Crews are also installing micro piles for foundations in the elevator area.  All in all, a busy and productive week.