• Concrete has been poured for the foundation of new Fellowship Hall (see picture).
  • Concrete completed for the walkway between admin building and Barron Hall
  • New power supply added to Admin building to allow for new installation requirements
  • Drywall and insulation started on both floors of the admin building

BurWil also submitted their proposed shoring and underpinning solutions for the eventual elevator. In the menatime, they continue to dig the pit. We expect to see several inspections from the city next week that will allow for additional work to be completed. 

It has been exciting to see all of the recent activity!