The elevator pit has been backfilled with dirt and rock to allow a pad for drilling equipment. Next week samples are planned to determine the extent of the rock in this area.
Much of the other noticeable work is in Zone B (admin). Electrical crews have started rough in work for placement of electrical boxes, and the low voltage team is now planning for their internet drops.
Additionally, the covered pathway between Barron Hall and Zone B is under heavy construction with concrete removal in this area (see picture).
Preliminary work continues on the expansion of the Reception Room. The extended room will become a mid-size Fellowship Hall/small gathering area.