It’s been a busy week for the construction team. Several large items have been accomplished:
As the picture shows, the final dormer was added to the admin building (Zone B).
Perhaps most significantly, the construction team elected to change course on digging for the elevator pit (Zone C). Originally, they had planned to wait approximately a month for a testing. Due to the prolonged time, the company began digging in the area to get a better idea of the amount of rock involved. As a result, a large amount of excavation has been completed!
Demolition work in the basement and long hallway from chapel to Spitzer (Zone D) is now complete. That area is completely blocked off and inaccessible. The bathrooms adjacent to the Spitzer Building foyer are still available.