The contractor has began its infil on the 2nd floor of the admin area. The picture reflects the area where the stairs originally were located. This provides much more space on the 2nd floor where a conference room is planned.
As previously discussed, the location of the elevator is on hold until a contractor can drill in the area to find the depth and size of the rock needed for removal. Since this area is presently on hold, the contractor plans to move earlier than planned to Zone D – defined as the area from the Sanctuary to Spitzer building.
The hallway from the Chapel to the Spitzer lobby is planned to undergo construction shortly. Hence, it will not be accessible in the near future. The bathrooms at the end of the hallway, just before the lobby, are still accessible.