Weather affected progress this week with Monday being unavailable for work with ice from the weekend. The elevator area was flooded from the rain and required a pump, some of that water frozen. This slowed further concrete work since site was not ready. Some progress as we continued the week. Our next scheduled meeting is on Wednesday to talk about way forward.

Chapel Hallway (Zone D): HVAC laid out registers; electric rough in continues

Sanctuary: new chancel handrails have been painted