barron hall connector
Read more about our updates in the weekly email from Pastor Jay’s desk!
construction update
Drywall in Zone D (the Chapel hallway). Read more about our updates in the weekly email from Pastor Jay’s desk!
week 51
Weather affected progress this week with Monday being unavailable for work with ice from the weekend. The elevator area was flooded from the rain and required a pump, some of that water frozen. This slowed further concrete work since site was not ready. Some progress as we continued the week. Our next scheduled meeting is on Wednesday to talk about way forward.
Chapel Hallway (Zone D): HVAC laid out registers; electric rough in continues
Sanctuary: new chancel handrails have been painted
Week 50
Excavation work for the grand hallway!
Admin Area (Zone B): The columbarium is now complete.
Chapel Wing (Zone D): work/planning for collapsible walls and brickwork outside of the smaller fellowship hall.
Restrooms on the west end are still inaccessible.
Week 48
Foundation walls and slab for elevator shaft are complete! Installation of concrete block walls has started.
Chapel Wing (Zone D): Concrete poured for the ramp that leads from the vestibule to the Chapel.
Restrooms on the west end are still inaccessible.
weeks 45-47
Work has continued at a reasonable pace during December. Most of the current work is concrete cutters removing the old Sanctuary stairs, prepping the new ramp for concrete pour in Zone D, and prepping elevator area for concrete walls. Bathrooms in the Chapel hallway have been demo’d…design team working on flooring, wall, and countertop options. We expect work to slow during the next 2 weeks with the holidays.
Week 44
- Footings Dug for foundation
- Rebar install prior to concrete pour
- Concrete base slab poured
- Concrete tested, rebar verified by ind team
- Rough framing of walls
- Tie in new water to construction area
- Exhaust vent installed in roof
- Finish rough wood frame
- Demo mens/womens bathrooms
- Dig out ramp area, prep for concrete
Sanctuary
- Paint stairwell up to balcony
- Porte cochere timber replacement
Week 43
- Roofing work complete with slate being added.
- Electrical Rough-In is ongoing.
- Plumbing has been inspected.
- Next up: Fur out walls and frame in columns.
- The rebar is onsite and the plan is finalized for the elevator pit.
- Crews working to prep the layout for a concrete pour.
The Sanctuary Balcony is OPEN! We are expecting a new paint job, but it is accessible and usable for all services.
week 41
Back in the Sanctuary!
Enter through the doors to the new vestibule by the porte cochere (see image below). Note: The new restrooms are not yet complete. Restrooms available on all levels of the Spitzer Building..
